bypass of Malters had to be reconstructed during 9 months
approximately. Therefore on lane had to be closed. The entire
traffic flow had to drive through the villages.
In
each of the two junctions in Malters/LU traffic lights had to be installed (not only the 4 traffic arms
but also the pedestrian crosswalk had to be taken into account). Additionally the units were equipped with a bus priority.
During the peak hours the units were corresponding to each other.
other.

Temporary traffic light unit in Malters/LU, view from the main street

The same crossing view from the junction.

On the basis “UG 6” Control unit based on UG 6 and especially expanded
to meet the expectations in Malters. Programming via touch screen and analyses electronic of public transportation.
|
|
|